Wednesday, 13 October 2010

Production Schedule


29th October 2010 AM
Filming:
·         Richmond Park
·         Richmond Bridge
Props:
·         Necklace
·         Rose
Actors:
·         Main protagonist-Harley
·         Ex-boyfriend-Rochelle
Filming equipment:
·         Boom mic
·         Camera
·         Tri pod
29th October 2010 PM
Filming:
·         Bus stop, Kingston
Props:
·         Phone
·         Necklace
Actors:
·         Main protagonist-Harley
·         Friends-Carla & Chloe
Filming equipment:
·         Camera
·         Tri pod
Contingency plan
If there are any issues with actors not being available, problems with equipment/props etc we will be able to film on Saturday 30th October and Sunday 31st October.
If there is bad weather we will also need extra props of umbrellas for the cast/crew and we will also be needing a helper to hold an umbrella over the camera.